Starting November 1, Front Beach parking stations stop charging. The beach has already switched to its long off-leash window for dogs. In a normal year those are the first signs that the stretch from Breach Inlet to the Isle of Palms Pier is going quiet. In 2026, the same weeks are when the City of Isle of Palms plans to start pumping sand onto that stretch. It is the last and longest leg of a renourishment project that has run along the Wild Dunes shoreline since late July. The city's tentative schedule puts the first day of pumping in Reach 3 at November 1, allows 45 days, and sets demobilization for December 15.
The date is the least settled part of the plan. The north end's summer and early fall show why.
What Reach 3 Covers
The engineering firm, Coastal Science & Engineering, defines Reach 3 as Breach Inlet to the Pier. In CSE's June 24 presentation to City Council, that comes to 8,600 feet, about 1.6 miles, and 800,000 cubic yards of sand. It is the longest of the three reaches. Reach 1, from the Wild Dunes Property Owners Beach House to the Wild Dunes Links Golf Course, runs 4,800 feet. Reach 2, from 53rd Avenue to the Beach House, runs 5,800 feet.
The pre-construction plan sheet for Reach 3 marks Breach Inlet, the Sea Cabins, the Pier, and beach access points 2 through 9 along the corridor. It also notes that crews may adjust the dune alignment in the field. Several design details matter to anyone who walks this beach regularly:
- A built dune along most of the beach south of 9th Avenue, planted once the project ends
- A dune elevation of 14 feet NAVD and a berm at 6 to 7 feet, with a maximum berm width of roughly 325 feet
- No work on or under private decks, patios, porches or erosion-control structures
- Sand dredged from an offshore borrow site about two miles southeast of the Island Pier
Reach 3 also has its own funding arrangement. The Wild Dunes Community Association pays 53% of the north-end cost, and the city pays the other 47%. The city covers the south end on its own: about $5.66 million of the $7.16 million cost for Reach 3, with a $1.5 million state grant making up the rest. The city has received $1.5 million of the $5.3 million it requested from the state, and that money goes to Reach 3. Across all three reaches the project totals 2.5 million cubic yards and $22.39 million.
The Schedule So Far
The north end's progress is the best guide to how Reach 3 will go. The table below compares three versions of the timeline: CSE's June forecast, the city's revised dates, and what actually happened.
| CSE forecast, June 24 | City's revised date | What happened | |
|---|---|---|---|
| Reach 1 start | July 17 | July 27 | Pumping began July 27 near Mariner's Walk |
| Reach 1 finish | 50 days planned | 50 days planned | Finished Aug. 30, in about 35 days |
| Reach 2 start | Sept. 9 | Sept. 1 | Pumping began Aug. 31 |
| Reach 2 finish | 45 days planned | 45 days planned | Nearly 90% complete as of Oct. 5 |
| Reach 3 start | Nov. 1 | Nov. 1, tentative | Not yet started |
Reach 1 went better than planned. Pumping paused in mid-August for dredge repairs, with about 350,000 cubic yards placed by August 13, and the reach still wrapped up in about 35 of its 50 planned days. Live 5 reported on September 2 that the first phase finished more than two weeks early and that Reach 2 started within 24 hours.
Reach 2 has followed the weather. The city's updates record weather downtime in early September before dredging resumed on September 10. They also record weather-related staging in the harbor plus routine repairs on September 23 and 24, and a main-engine repair on September 28, when the crew moved roughly 12,000 cubic yards. On October 1, Marinex was pumping in front of Seagrove Lane, had passed 540,000 cubic yards in Reach 2, and planned to take the dredge to safe harbor ahead of a forecast nor'easter. The October 5 update said the dredge was headed to Charleston Harbor for several days of rough offshore conditions. Crews had finished through the Seagrove Villas area, and the contractor still expected Reach 2 to be complete by the end of the week.
Since September, then, the days lost have come from the ocean, not the beach. Reach 3 is set for the latest weeks of the season. The 45 days allowed for it equal Reach 2's planned length, and Reach 2 is still running after its fourth trip to the harbor. CSE's own June slide for Reach 3 gives the work window as "Oct-Early Nov 2026," while its timetable and the city's schedule both say November 1. All of these dates were set before Reach 2's fall delays.
A July report from Count on 2 described a proposed Reach 3 start between Fifth and Seventh Avenues, working north toward the Pier and then south toward Breach Inlet. That was an early plan. The city's numbered updates have announced each change in location as it happened, and they are the place to watch for where Reach 3 will start.
A Morning Walk With a Pipeline on the Beach
The beach stays open. According to the city's FAQ, crews work in sections of roughly 300 yards. Pedestrians can usually walk around the fenced work zone, except for brief restrictions during dune construction, and sand ramps let beachgoers cross the dredge pipeline to reach the water. Before construction began, Mayor Pro Tempore Scott Pierce told Live 5 that visitors might have to walk 100 to 200 feet to get around the work, and that the city planned to keep access open on both sides. During Reach 1, the beach stayed open everywhere except right next to the active work, according to the Post and Courier.
The overlap with fall routines will be easy to see on the south end. The city's beach rules let dogs off leash from 4 p.m. to 10 a.m. between September 15 and March 31, and owners still need a leash in hand, voice control and cleanup. Those early-morning and late-afternoon hours now fall alongside fenced zones, heavy equipment and pipe crossings. In July, Mayor Phillip Pounds told ABC News 4 that the round-the-clock work would bring lights, noise and backup alarms, and he asked beach users to take care around the temporary pipe crossings.
The night work moves quickly. The city expects progress of 100 to 300 feet a day and says the disturbance in any one area should pass within a night or two. The city has also posted a short video, "What will construction sound like?," for anyone who wants to hear it before the pipe reaches their stretch.
The work comes in the off-season this year because of a decision about cost. The city says starting construction in the summer saved about $10 million compared with other schedules. That saving explains why Wild Dunes had dredge lights in July, and why the south end's turn falls in late fall.
Front Beach Before the Pipe Arrives
The October calendar on the south end runs ahead of the dredge. Ghostly Tide Tales brings free campfire storytelling to Front Beach on Friday, October 16, from 6 to 7 p.m., with access beside the Sea Cabins. This year the city is promoting more fire barrels and a new storyteller. The Halloween Golf Cart Parade & Carnival runs October 31 from 4 to 6 p.m. Lineup starts at 3:30 p.m. on 27th Avenue, and the carnival has a drive-through haunted house, inflatables, food vendors and trick-or-treat bags.
October 31 is also the last day of paid parking. The city's parking page enforces paid parking in municipal lots and at the Front Beach on-street stations from March 1 through October 31, 8 a.m. to 8 p.m. Free parking and the tentative Reach 3 start therefore begin on the same day. Heavy's Barburger is on Ocean Boulevard at Front Beach and lists itself as open Tuesday through Sunday. November's city calendar has a Sea Stroll & Learn on November 12 and Coffee & Canines on November 14, both inside the planned Reach 3 window.
What Comes After the Sand
The city is already looking at ways to make this sand last longer. Council hired Foth/Olsen to review its beach restoration strategy, and the city has said any recommended alternatives would need to go in within a few years of the 2026 project to get the most out of the new sand. Foth/Olsen's findings, dated September 2, looked at several options: doing nothing, scheduled or triggered renourishment, disposal in the Breach Inlet waterway, shoal management at Dewees Inlet, a terminal groin, and possible breakwaters or geotubes. The firm presented to Council on September 22. The Beach Preservation Committee's October 1 agenda included discussion of a request for proposals covering the feasibility, design, permitting and construction administration of a terminal groin and shoal management. The city plans to attach Foth's final written report and the latest beach-monitoring report to that request once both are available.
Until then, Reach 3 runs on the dates the city publishes in its numbered updates. Dune planting follows construction, and demobilization is penciled in for December 15.
If you own on the south end and want to understand what a rebuilt dune and wider berm mean for your property's story, Smith and Ryan Group is glad to walk the stretch with you once the pipe moves on. You can request a private consultation or a complimentary home valuation whenever it suits you.